Flickr

Wednesday, June 28, 2023

On Digital camera, Half Of Below-Building Bridge Collapses In Chhattisgarh

On Digital camera, Half Of Below-Building Bridge Collapses In Chhattisgarh [ad_1]

The bridge is being constructed at a price of Rs 16 crore.

Raipur:

A portion of a Rs 16-crore under-construction bridge collapsed and was washed away in Chhattisgarh immediately. The realm had witnessed steady rain for 4 days and native residents, who had gone to the bridge to test the water degree of the river under it, have been standing very near the construction when it collapsed. 

Native authorities have, nonetheless, stated that the construction that caved in consisted of solely the "staging and shuttering" accomplished by the contractor, and no concrete had been poured. They added that a show-cause discover might be issued to the contractor.

The bridge is being constructed at Sagni Ghat in Durg district to attach the Silli and Nankatti villages. The ghat is named Triveni Sangam as a result of it sees the confluence of three rivers - Shivnath, Aamner and Sagni. 

Building on the bridge, which is estimated to value Rs 16.4 crore, had begun on November 11, 2020, and it was alleged to have been accomplished on April 11, 2022. 

Movies present the construction starting to buckle earlier than crumbling right into a heap and getting washed away by the river. Native residents might be seen standing close to its edges because it collapsed. 

Officers stated it has been raining incessantly in Durg division for the previous 4 days, due to which 24 thousand cusecs of water had been launched into the Shivnath river from the Mogra reservoir. They stated the construction couldn't take the strain of the elevated water circulation and caved in.

D Ok Maheshwari, government engineer of the bridges division, stated the contractor, Amar Infrastructure, had been requested to dismantle the construction forward of the monsoon season, nevertheless it failed to take action. 

"These directions are issued to all contractors forward of the wet season. Regardless of this, the contractor had not dismantled the construction on the Sagni Ghat bridge. Solely the staging and shuttering have been washed away. No concrete had been poured," stated Mr Maheshwari.

"The injury, of round Rs 12 lakh, might be borne by the contractor and a show-cause discover will even be issued," he added. Requested in regards to the delay within the bridge's completion, he stated it was due to points associated to land acquisition. 

A portion of a bridge in neighbouring Bihar's Kishanganj district caved in on Saturday, barely three weeks after a portion of an enormous Rs 1,700-crore under-construction bridge over the Ganga had collapsed within the state's Khagaria district. 


[ad_2]

0 comments